Geography Department

Main Menu

Spirit

Department Expectations

Year 7

Year 8

Year 9

Year 10

Year 11

Click here to return to the Scarborough Photo Album

The information on these pages is taken from a report published by Scarborough Council's web site (www.e-sbc.co.uk) and is available in Adobe Acrobat Format from this link:-

http://www.e-sbc.co.uk/pdf_files/coast_protection/scarborough_coast_protection_works.pdf

The file is 567Kb in size, and is reproduced here because it sometimes takes a long time to load.

East Pier, Castle Headland and The Holms, Scarborough - Coast Protection Works

The information contained on these pages in relation to these works will detail the following: -

Mission Statement - by Partners to the Scheme (Scarborough Borough Council, Edmund Nuttall Ltd. and High-Point Rendel)

"To deliver a sustainable project safely and on time in a technically, environmentally and costeffective manner to the benefit of all stakeholders".

The Site: -

Back to top of page

 

The Need for the Coastal Protection works

Scarborough Coastal Defence Strategy Study (Holbeck to Scalby Mills), Carried out by the Borough Council's consultants, High-Point Rendel has determined the following: -

  • Limited residual life of the existing coastal defence structures,
  • Severe wave overtopping resulting from near vertical seawalls and breakwaters, low crest elevations and in places low foreshore elevations,
  • Residual landslide risk with significant problems associated with major first time failures caused by renewed cliff foot erosion, expansion of shallow landslides, extreme groundwater levels, slope drainage failures and also major reactivation of pre-existing failures
Key Problems
  • Ageing coastal protection structures (18th to early 20th century structures with limited residual life),
  • Overtopping,
  • Residual landslide risk,
  • Potential for loss of structures and loss of protection,
  • Threat to public safety,
  • Threat to protected assets (Estimated at approximately £ 100 million)

Back to top of page

The Scheme Objectives

(East Pier, Castle Headland and The Holms)

The objectives for these priority coastal works established in the strategy study are: -

  • Coastal protection to be structurally sound and with a future design life of at least 50 years,
  • Minimise ongoing maintenance of the coastal protection structures,
  • Limit overtopping to reduce storm damage and impact of storm events on the Harbour,
  • Marine Drive and the Holms,
  • Meet Environmental Objectives,
  • Reduce the risk of danger to the public.

Back to top of page

The Problems - East Pier

Picture above shows the East Pier, Scarborough - The daily challenge.

  • It is an ancient Grade II Listed Structure (c. 1732 & earlier),
  • Consists of a rubble filled dressed masonry structure founded on rubble rock bund,
  • Sea wall masonry in poor condition with remaining residual life low,
  • Apron deteriorating with extensive rehabilitation required,
  • Overtopping of the pier causes regular wave disturbance in the Outer Harbour and hazard to users of the East Pier and Outer Harbour.

Back to top of page

The Options Considered - East Pier

  • Do nothing,
  • Do minimum (minimum maintenance),
  • Re-build on existing line,
  • Construct a new sea wall seaward,
  • Offshore breakwater.
Viable Options - East Pier

Rock armoured revetment: -

  • Rock revetment at 1:4 slope armoured with 9-18 tonne rock due to aggressive wave climate,
  • Covers and protects entire existing bund,
  • Meets design life criteria,
  • Overtopping significantly reduced,
  • Significant future maintenance still required,
  • Construction problems,
  • Highly visible structure.

Accropode armoured revetment: -

  • Accropode revetment at 1:5 slope with 6.3 & 9 metre cubed accropodes,
  • Toe of new structure on existing bund, toe detail must address erosion problem,
  • Meets design life criteria,
  • Minimum future maintenance,
  • Overtopping significantly reduced,
  • Construction problems less than with rock armour,
  • Less visible structure than rock revetment.
The Problems - Castle Headland

Regular and costly damage to the infrastructure of Marine Drive is shown in the photographs above.

  • Concrete sea wall with road behind,
  • Concrete deteriorating with extensive rehabilitation required,
  • Some erosion at toe of wall,
  • Increased overtopping of the sea wall causes regular road closures (>35/year)

The deteriorating structure of the Marine Drive is shown in these images..

Viable Options - Castle Headland & The Holms

Rock armoured revetment: -

  • Option comprises strengthening of existing wall and construction of new rock bund,
  • Wave wall constructed to reduce overtopping,
  • Meets design life criteria,
  • Minimum future maintenance requirements met at The Holms (but not at Castle Headland),
  • Significant construction problems along Castle Headland,
  • Highly visible structure along Castle Headland.

Accropode armoured revetment: -

  • Option comprises rehabilitation of existing wall and construction of new Accropode armoured bund,
  • Wave wall constructed to reduce overtopping,
  • Meets design life criteria,
  • Minimum future maintenance requirements,
  • Steeper slope than rock schemes: accropodes are more efficient than rock armour for hydraulic stability,
  • Less visible structure than rock revetment at Castle Headland, (no significant difference at The Holms).

Back to top of page

The Preferred Scheme

Rocks or Accropodes?

Accropodes are an interlocking concrete armour unit, they are more efficient than rock for the revetment armour as: -

  • They interlock and thus a lighter unit can be used for given wave conditions. This allows
  • steeper slopes to be used for revetment design.
  • They have a greater percentage of voids and therefore the overtopping for given wave
  • conditions and slope is less.

The photograph above shows a scheme elsewhere where rock & accropodes have been successfully used.

Accropodes may have a stronger visual impact than rock armour, this is significantly offset however by: -

  • The smaller profile of an accropode armoured bund, smaller volume of material, lower intrusion into inshore waters (navigation, fisheries and foreshore),
  • The smaller size of the individual units,
  • Lower overall capital costs,
  • Greater stability and lower maintenance (critical).
Wave Overtopping

Existing overtopping on Marine Drive is up to 320 litres/second/metre under ten year return period storms. This causes the closure of Marine Drive some35 times per year causing damage to the seawall, pavement and road. The provision of an accropode revetment with a 1m high wave return wall will allow for overtopping to be reduced to levels of 10 litres/second/metre or less, thereby significantly reducing the risk of damage to the Marine Drive and greatly enhancing the safety of its users.

From a technical viewpoint, the construction of a revetment along the seaward face of the wall best addresses the scheme objectives.

The scheme comprises an accropode protected revetment along the East Pier and Castle Headland and rock armour along The Holms. This is has been determined upon the following factors: -

  • Environmental: Reduced visual impact and minimum foreshore cover,
  • Stability and reduced maintenance,
  • Easier constructability,
  • Lower overall construction costs (£ 26 million)

Back to top of page

Approval & Consultation Process

  • Council Approval of preferred scheme,
  • Scheme public consultation process involved the following: -
  • Coast Protection Act 1949 (Notification of scheme under Section 5),
  • FEPA (1985) Licence to DEFRA (Licence to deposit material below High Water Mark)
  • Section 34 of Coast Protection Act 1949 - (DETR Ports Division for works below High Water Mark)
  • Listed Building Consent for East Pier - (Grade II Listed Structure)
  • Planning Application & Approval from Planning Authority

Back to top of page

Tender Award

Scheme received approval from DEFRA who awarded 75% Grant Aid. The Tendering Selection Process began by advertising in the European Journal which attracted interest from companies all over Europe. This was eventually reduced down to 5 companies who were invited to tender for the job.

In March 2002 the contract was awarded to Edmund Nuttall Ltd. of Newcastle.

  • Contract Period of 22 months,
  • Contract Value Total of £ 26 million.

The Contractor & The Works - Edmund Nuttall Ltd.

Edmund Nuttall Ltd. are committed to successful partnering, health & safety issues, quality assurance, environmental factors & people. This contract is being run from their North East office which is based in Newcastle. The photograph below shows an illustration of an accropode arrangement to revetment.

Back to top of page

Programme of Works

The chart above details the programme of works set down by Edmund Nuttall Ltd. As can be seen from the chart, they have provisionally decided to 'demobilise' site activities on the Castle Headland & The Holms during October to March 2002/03, times of the year when severe weather conditions could hamper the progress of the job. 7 days a week, 24 hours a day working is to be used to take full advantage of the tides and sea conditions.

Back to top of page

The Methods of Construction

The photograph below shows the type of machinery that will be used to remove the dumped rock from the North Bay beach area at low water and moved to site up along ramps along the Marine Drive and placed in position. Works will progress north to south.

The above photographs illustrate the type of activity to be undertaken in placing the rock armour.

This picture below shows an example of a De Zeebouwer Jack-Up barge complete with cantilever sliding frame which will be used for drilling the toe piles. Toe piling is essential to hold the revetment securely in place.

Thank you for taking the time to visit these pages and we do hope that they are of interest to you or your organisation. If you have any comments to make, please do not hesitate to get in touch.

 

Further Information

Watch out for the Monthly Bulletin Sheets of what activities are taking place in the next few weeks.

A public exhibition about these works is currently running at the Corner Complex, North Bay,

Scarborough throughout the duration of the works. Please feel free to visit.

 

 

 

 

 
Useful Links

Main Contractors Web-Site address: - www.edmund.nuttall.co.uk

Consultants/Site Supervisors Web-Site address: - www.highpointrendel.com

Government Funding Office: - www.defra.gov.uk